EU Parliament Backs 300-Day Cap on Environmental Assessments
26 November 2026 · ACSINTE & PARTNERS

English version below
Ce s-a schimbat
La 25 noiembrie 2026, Parlamentul European a adoptat, în plenul de la Strasbourg, poziția sa de negociere asupra Propunerii de Regulament al Parlamentului European și al Consiliului privind accelerarea evaluărilor de mediu – COM(2025) 984 din 10 decembrie 2025, procedura 2025/0391(COD). Votul a fost strâns – 367 pentru, 268 împotrivă, 25 de abțineri – iar raportul a fost retrimis comisiei ENVI pentru negocierile cu Consiliul. Propunerea face parte din pachetul de simplificare „Omnibus VIII” pentru legislația de mediu.
Actul propus este un regulament, direct aplicabil în toate statele membre, fără transpunere. El nu modifică fondul Directivei 2011/92/UE privind evaluarea impactului asupra mediului (EIA), al Directivei 2001/42/CE privind evaluarea strategică de mediu (SEA), al Directivelor „Habitate” (92/43/CEE) și „Păsări” (2009/147/CE) sau al Directivei-cadru privind apa (2000/60/CE), ci impune reguli procedurale comune pentru aplicarea lor.
Elementele principale ale textului Comisiei, păstrate de Parlament:
- un punct unic de contact pentru mediu, pe care statele membre trebuie să îl desemneze în 6 luni de la intrarea în vigoare, ca interlocutor unic al dezvoltatorului;
- proceduri coordonate sau comune atunci când același proiect intră sub incidența mai multor directive, cu un singur aviz privind domeniul evaluării;
- termene maxime obligatorii pentru fiecare etapă: 60 de zile pentru încadrare (45 de zile pentru modificări sau extinderi de proiecte), 30 de zile pentru avizul privind domeniul evaluării, 30–90 de zile pentru consultarea publicului, 30 de zile pentru confirmarea caracterului complet al documentației și 90 de zile pentru concluzia motivată, cu o prelungire excepțională de cel mult 30 de zile;
- modificările și extinderile de proiecte (reconversii industriale, prelungirea duratei de funcționare, decarbonizare) sunt supuse doar încadrării, evaluarea completă fiind cerută numai pentru lucrări majore cu riscuri similare sau mai mari decât ale proiectului inițial;
- digitalizare: depunere electronică la 6 luni de la intrarea în vigoare, portal digital central la 12 luni și proceduri complet digitalizate la 24 de luni;
- o „cutie de instrumente” pentru proiectele din sectoare strategice – prezumția interesului public superior, aprobarea tacită a unor etape intermediare dacă autoritatea nu răspunde în termen, tratarea prioritară a litigiilor – aplicabilă acolo unde legislația sectorială a UE definește deja proiecte strategice;
- uciderea sau perturbarea ocazională a speciilor protejate în timpul execuției sau exploatării nu este considerată „deliberată” dacă s-au adoptat măsuri de atenuare adecvate și proporționale.
Poziția Parlamentului plafonează durata totală a evaluării de mediu, inclusiv încadrarea, la 300 de zile, cu o prelungire de cel mult 60 de zile în cazuri excepționale (față de 30 de zile în propunerea Comisiei). La articolul privind speciile protejate, plenul a reținut un compromis potrivit căruia uciderea sau perturbarea accidentală, inclusiv deteriorarea accidentală a cuiburilor și a ouălor, nu este considerată intenționată dacă există măsuri de atenuare, s-au avut în vedere cele mai bune tehnici disponibile, s-au evaluat efectele cumulate și nu se deteriorează starea de conservare a populației. Printr-un amendament adoptat cu 357 de voturi la 284, Parlamentul cere Comisiei ca, în 12 luni de la intrarea în vigoare, să prezinte o revizuire cuprinzătoare a Directivelor „Habitate” și „Păsări”, urmată de o propunere legislativă.
Consiliul își adoptase mandatul la 30 septembrie 2026, cu o listă exhaustivă a proiectelor strategice, termene mai lungi decât cele propuse de Comisie și extinderea prevederilor privind speciile la activități recurente precum silvicultura. Trilogurile pot începe acum; Președinția Consiliului urmărește un acord până la sfârșitul anului 2026.
Cine este afectat
Regulamentul vizează orice proiect supus evaluării impactului asupra mediului sau încadrării în România: parcuri eoliene și fotovoltaice, stocare, linii și stații electrice, centre de date, fabrici și extinderi industriale, infrastructură de transport, proiecte imobiliare mari și ansambluri de locuințe. Sunt vizate și planurile și programele supuse evaluării strategice (planuri urbanistice generale și zonale), cu termene de 90 de zile pentru încadrare, 40 de zile pentru definirea domeniului și 7 luni pentru raportul de mediu.
În România, procedurile relevante sunt cele din Legea nr. 292/2018 privind evaluarea impactului anumitor proiecte publice și private asupra mediului, Hotărârea Guvernului nr. 1.076/2004 privind stabilirea procedurii de realizare a evaluării de mediu pentru planuri și programe și Ordonanța de urgență a Guvernului nr. 57/2007 privind regimul ariilor naturale protejate. Odată adoptat, regulamentul se va aplica direct, iar termenele naționale mai lungi vor trebui aliniate; cele mai scurte rămân valabile.
Ce au de făcut companiile acum
- Cartografiați proiectele aflate în pregătire sau deja în procedură de mediu și identificați-le pe cele care ar putea fi „strategice” potrivit legislației sectoriale a UE (industria cu zero emisii nete, materiile prime critice, rețelele electrice): acestea ar beneficia de prezumția interesului public superior și de procedurile accelerate din anexă.
- Revizuiți calendarele și contractele proiectelor (EPC, finanțare, PPA, antecontracte) în care durata obținerii acordului de mediu este o condiție suspensivă sau un risc alocat: termenele maxime și interdicția de a mai cere informații noi după confirmarea dosarului complet schimbă negocierea clauzelor de întârziere.
- Pregătiți documentația după standardul „dosar complet de la început”: termenele curg numai de la depunerea tuturor informațiilor cerute, iar argumentele neridicate în faza administrativă pot fi excluse din litigii; documentarea măsurilor de atenuare pentru speciile protejate devine esențială pentru apărarea ulterioară a autorizației.
Date-cheie
- 30 septembrie 2026 – Consiliul UE adoptă mandatul de negociere.
- 25 noiembrie 2026 – plenul adoptă poziția Parlamentului (367 la 268, 25 abțineri).
- Sfârșitul anului 2026 – ținta Președinției Consiliului pentru un acord politic.
English version
What changed
On 25 November 2026 the European Parliament, sitting in plenary in Strasbourg, adopted its negotiating position on the Proposal for a Regulation of the European Parliament and of the Council on speeding-up environmental assessments – COM(2025) 984 of 10 December 2025, procedure 2025/0391(COD). The vote was tight – 367 in favour, 268 against, 25 abstentions – and the report was referred back to the ENVI committee for the negotiations with the Council. The proposal is part of the “Omnibus VIII” simplification package for environmental legislation.
The proposed act is a regulation, directly applicable in all Member States without transposition. It does not change the substance of Directive 2011/92/EU on environmental impact assessment (EIA), Directive 2001/42/EC on strategic environmental assessment (SEA), the Habitats Directive (92/43/EEC), the Birds Directive (2009/147/EC) or the Water Framework Directive (2000/60/EC); it imposes common procedural rules for their application.
The main elements of the Commission text, kept by Parliament:
- an environmental single point of contact, which Member States must designate within 6 months of entry into force, acting as the developer’s sole interlocutor;
- coordinated or joint procedures where the same project falls under several directives, with a single scoping opinion;
- binding maximum deadlines for each step: 60 days for screening (45 days for changes or extensions of projects), 30 days for the scoping opinion, 30–90 days for public consultation, 30 days to acknowledge the completeness of the file and 90 days for the reasoned conclusion, with an exceptional extension of at most 30 days;
- changes and extensions of projects (industrial repurposing, extension of the operating period, decarbonisation) are subject only to screening, a full assessment being required only for major works posing risks similar to or greater than those of the original project;
- digitalisation: electronic submission 6 months after entry into force, a central digital portal after 12 months and fully digitalised procedures after 24 months;
- a “toolbox” for projects in strategic sectors – presumption of overriding public interest, tacit approval of certain intermediate steps if the authority does not reply within the deadline, priority treatment of disputes – applicable where sectoral EU legislation already defines strategic projects;
- occasional killing or disturbance of protected species during construction or operation is not considered “deliberate” where appropriate and proportionate mitigation measures have been adopted.
Parliament’s position caps the total duration of the environmental assessment, including screening, at 300 days, with an extension of at most 60 days in exceptional cases (compared with 30 days in the Commission proposal). On the protected species article, the plenary kept a compromise under which accidental killing or disturbance, including accidental damage to nests and eggs, is not considered intentional where mitigation measures are in place, best available techniques have been considered, cumulative effects have been assessed and the conservation status of the population does not deteriorate. Through an amendment adopted by 357 votes to 284, Parliament asks the Commission to present, within 12 months of entry into force, a comprehensive review of the Habitats and Birds Directives, followed by a legislative proposal.
The Council had adopted its mandate on 30 September 2026, with an exhaustive list of strategic projects, longer deadlines than those proposed by the Commission and an extension of the species provisions to recurring activities such as forestry. Trilogues can now begin; the Council Presidency is aiming for an agreement by the end of 2026.
Who is affected
The regulation covers any project subject to environmental impact assessment or screening in Romania: wind and solar parks, storage, power lines and substations, data centres, factories and industrial extensions, transport infrastructure, large real estate projects and housing developments. It also covers plans and programmes subject to strategic assessment (general and zonal urban plans), with deadlines of 90 days for screening, 40 days for scoping and 7 months for the environmental report.
In Romania, the relevant procedures are those under Law No 292/2018 on the assessment of the impact of certain public and private projects on the environment, Government Decision No 1,076/2004 establishing the procedure for environmental assessment of plans and programmes and Government Emergency Ordinance No 57/2007 on the regime of protected natural areas. Once adopted, the regulation will apply directly and longer national deadlines will have to be aligned; shorter ones remain valid.
What companies should do now
- Map the projects in preparation or already in the environmental procedure and identify those that could qualify as “strategic” under sectoral EU legislation (net-zero industry, critical raw materials, electricity grids): these would benefit from the presumption of overriding public interest and the accelerated procedures in the annex.
- Review project timetables and contracts (EPC, financing, PPAs, pre-sale agreements) in which the time needed to obtain the environmental permit is a condition precedent or an allocated risk: the maximum deadlines and the ban on requesting new information after the file is acknowledged as complete change the negotiation of delay clauses.
- Prepare documentation to the “complete file from day one” standard: deadlines run only from the submission of all required information, and arguments not raised at the administrative stage may be excluded from litigation; documenting mitigation measures for protected species becomes essential for later defending the permit.
Key dates
- 30 September 2026 – the Council of the EU adopts its negotiating mandate.
- 25 November 2026 – the plenary adopts Parliament’s position (367 to 268, 25 abstentions).
- End of 2026 – the Council Presidency’s target for a political agreement.
This article provides general information and does not constitute legal advice.
- COM(2025) 984 – Proposal for a Regulation on speeding-up environmental assessments (EUR-Lex)
- European Commission – Environmental omnibus package of 10 December 2025 (DG Environment)
- Council of the EU – Council agrees negotiating stance to fast-track environmental assessments (30 September 2026)
- European Parliament – Legislative Observatory, procedure 2025/0391(COD)
- European Parliamentary Research Service – Omnibus VIII: speeding-up environmental assessments (plenary at a glance)
- Agence Europe – Parliament adopts position on speeding-up environmental assessments (25 November 2026)